EXECUTIVE SUMARY
proyek kampung kuda kuningan,Kuningan Jawa barat
A.RENCANA PENERIMAAN
I.Penjualan Rumah T-69 (3unit) :Rp 2.393.009.856
Penjualan Rumah T-118 (3 unit) :Rp 3.476.399.808
II.Penerimaan kelebihan tanah :Rp 96.100.000
------------------------- +
TOTAL OMSET 5.965.509.664
RENCANA PENGELUARAN
--------------------------------------------------------------------------------------------------------------------------
I.BIAYA PEROLEHAN LAHAN :Rp.2.001.455.000 33.5%
(Termasuk fee perantara ,kompensasi,sertifikasi ,pajak,dll)
------------------------------------------------------------------------------------------------------------------------------------------------------
II,BIAYA PERIJINAN : Rp28.500.000 0,48%
(di kantor pemda dan pertanahan)
------------------------------------------------------------------------------------------------------------------------------------------------------
III.BIAYA PEMATANGAN LAHAN : Rp 216 .185.000 3,62%
(infrastuktur,utilitas,fasos,fasum pemeliharaan lingkungan)
------------------------------------------------------------------------------------------------------------------------------------------------------
IV.BIAYA BAYAR DI MUKA (OHC)
IV.1.Persiapan inventaris kantor :Rp 22.500.000 0,38%
IV.2.Operasional kantor .Rp .20.250.000 0,34 %
IV.3.Gaji karyawan :Rp.255.000.000 4,27%
IV.4.Bonus karyawan :Rp- %
IV.5.Promosi :Rp.65.000.000 1.09%
IV.6.Kesejahteraan :Rp.9.000.000 0,15%
------------------------------------------------------------------------------------------------------------------------------------------------------
V. BIAYA BUNGA
V.1.Pinjaman pembelian lahan : Rp.216.000.000 3,62 %
V.2.Kredit konstruksi : Rp.45.000.000 0,75%
------------------------------------------------------------------------------------------------------------------------------------------------------VI.BIAYA BANGUNAN
Bangunan 6 unit : Rp.1.220.610.000 20,46%
-------------------------------------------------------------------------------------------------------------------- --
VII.BIAYA LAIN-LAIN : Rp. 220.000.000 372 %
------------------------------------------------------------------------------------------------------------------------------------------------------
VIII.PENGEMBALIAN TITIPAN
VIII.1.Titipan Gimmick : Rp 144.000.000 2,41%
VIII.2 Titipan PPH Final : Rp. 150.000.000 2,51%
------------------------------------------------------------------------------------------------------------------------------------------------------
TOTAL PENGELUARAN : Rp 4.615.500.000 77,37%
LABA (After Tax)
=RENCANA PENERIMAAN-RENCANA PENGELUARAN : Rp 1.350.009.664 22.63%
A.LABA BAGIAN PENGELOLA (30%) : Rp.405.002.889
B.LABA BAGIAN PEMILIK MODAL (70) : Rp.945.006.765
KEBUTUHAN MODAL KERJA
PENGEMBALIAN MODAL KERJA
Dikembalikan di tanggal 14 Maret 2018
UMUR PROYEK : 15 Bulan
------------------------------------------------------------------------------------------------------------------------------------------------------
3 hal pokok dalam membuat executive summary bisnis plan
1. Berapa MODAL yang harus ditanam?
2. Berapa lama UMUR PROYEK?
3. Berapa LABA yang menjadi bagian investor?
postingan ini hanya sebagai acuan untuk nominalnya bisa berubah tergantung daerah dan tanggal pengajuan executive summarry bisnis plan
sumber referensi:http://ariwibowojinproperti.blogspot.co.id/